Sales hotline+86 135 1772 8899 | EmailQL8899@hotmail.com | WhatsApp+86 135 1772 8899
Genset HubDIESEL POWER · CHINA

Data centre backup power: UPS step load, harmonics and 10 kV connection

A data centre usually has N+1 generation already, so a mobile unit appears in only four situations: generator failure, fuel contamination, capacity during an expansion, or a bypass while a fixed set is serviced. Each has different requirements, but all of them come down to one question — can the unit hold a UPS load that steps from nothing to full in a tenth of a second?

Short answer: 1 MW of IT load at PUE 1.4 means about 1.4 MW total, so the vehicle is 1,600–2,000 kW — either two 1,000 kW units in parallel or one 2,000 kW medium-voltage unit. Total kW is not the constraint; the step load is. A rectifier front end can jump from 0 to 80–100%, so size the set at 1.4–1.6× the UPS rating unless the UPS has a generator mode (walk-in) with a controlled ramp.

Containerised diesel generator set being lifted by a mobile crane onto an equipment platform beside a building
Container set being lifted into position. Campus space is tight, so sets often go onto a platform or roof. The value of a mobile unit is that it occupies no permanent plant space — it covers an overhaul, an expansion or a failure, then leaves.

The step load is the real selection criterion

Ordinary load arrives gradually. A UPS does not. When mains fails, the UPS transfers to battery, the rectifiers reload, and the generator can see the load jump from 0 to 80% inside 100 ms. A synchronous machine rides that on excitation response and rotor inertia. Too small a set means voltage collapse and frequency dip; the UPS then rejects its input and transfers to bypass or shuts down — worse than an outage, because bypass exposes the load directly to mains.

UPS ratingRectifier loadSet without rampSet with walk-in
400 kVA~360 kW500–630 kW400–500 kW
800 kVA~720 kW1,000–1,250 kW800–1,000 kW
1,200 kVA~1,080 kW1,600–2,000 kW1,250–1,600 kW
2 × 800 kVA parallel~1,440 kW2 × 1,000 kW2 × 800 kW

Ranges are engineering experience, not guarantees. Check the UPS manufacturer's generator compatibility table: some ramp at 25%/s by default, some accept a 0→100% step, and some advise against generator operation entirely. Getting this wrong makes an oversized set useless.

Harmonics and derating

Six-pulse rectifiers commonly produce 25–30% THDi; twelve-pulse 8–10%; modular UPS with active PFC can reach 5%. A generator tolerates far less harmonic current than a transformer, because the additional copper and iron losses appear in the stator and exciter windings and can only leave through the set's own fan.

10 kV connection: the cable is the least of the savings

ConnectionCable at 1,000 kWVolt drop per 100 mSite requirement
0.4 kV LV4 × (3 × 240) mm² Cu, ~3.2 t per 100 m3–4%Spare LV breaker; drum needs craning
10 kV MV3 × 95 mm² Cu, ~0.3 t per 100 m<0.5%Spare ring-main way and protection settings

Three actions must be completed before energising an MV connection:

The chiller plant is the under-estimated single load

PUE 1.4 means roughly 400 kW of cooling behind 1 MW of IT, and chillers dominate it. Do not simply add the kW: check the largest single motor starting with everything else at full load. A centrifugal chiller draws 2–3× rated current on a soft starter and 1.1× on a VFD, but the start lasts 10–30 seconds — exactly when the UPS is also stepping.

A common and cheap fix: let the UPS carry IT load immediately, delay the chiller plant by 30–60 seconds in the BMS so the two transients do not coincide. That logic is worth more than one frame size of generator.

Space, exhaust and noise

Questions data centre teams ask

We have N+1 generators — why a vehicle?

Because N+1 fails together: generator breakdown, contaminated fuel, control-network loss, cooling water failure. The vehicle is an independent source that shares no fuel path, control system or safety boundary with the campus, which is why banks and cloud providers name it in their emergency plans.

What size for a 1,000 kVA UPS?

1,250 kW if the UPS supports walk-in; 1,600–2,000 kW if it does not. Base it on the manufacturer's compatibility table and a real step test, not on "UPS rating × 1.2".

Can a generator feed a UPS without damage?

Yes — rectifier load is routine duty for a modern set. The two risks are voltage collapse from undersizing and winding overheating from harmonics; the first is solved by selection, the second by derating and PMG excitation. What does damage a set is a small unit held at full load behind a large UPS for hours.

What does a 10 kV connection require?

A usable ring-main or switchgear way, licensed operators, a protection setting sheet and a permit from the site operator. Missing any one of them stops energisation — it is a process problem, not an equipment problem.

What about paralleling two vehicles?

Use a synchronising panel with check-sync, not a cable joint. Specify ±5% kW sharing, ±10% kvar sharing and reverse-power protection, and keep voltage and frequency droop characteristics close. Mixing brands works but takes far longer to commission.

Lead time and export?

45–70 days for standard configurations, 70–100 days for MV and paralleled systems. Sets and on-board electrical packages ship under HS 8502; whole-vehicle export needs destination approval and is normally handled by the converter partner.

Prefer paper? Download this brief as a one-page PDF — A4, English and Chinese, free, no form.