How a diesel generator ships from China: documents, packing and the cost nobody quotes

Most first-time import problems are not technical. They are paperwork, packing and port charges. This page walks through an order from deposit to arrival, names the documents you should receive, and flags the three places where buyers commonly lose money.

The order, step by step

  1. Load list and specification. You send required kW, voltage, frequency, application, altitude, ambient and destination port. We return a specification with a single-line diagram for review. This is where 80 % of later disputes are prevented — the voltage and rating definition must be written down, not assumed.
  2. Proforma invoice. Fixes the model, configuration, price, incoterm, payment terms, lead time and warranty. Check the alternator and engine serial prefix here, not after arrival.
  3. Deposit and production. Normally 30 % T/T in advance. Lead time is 15–25 days for stock ratings, 30–45 days for container modules or non-standard voltage.
  4. Factory test. Load test to nameplate with a printed report, plus a video for remote buyers. Insist on the serial number appearing on the report — a test sheet without it proves nothing.
  5. Balance payment and booking. 70 % before shipment, or against a copy of the bill of lading if the terms say so. We book the vessel and issue the loading plan.
  6. Documents and arrival. Originals or telex release, then destination clearance, then delivery to site and commissioning.

The document set

DocumentIssued byWhat it does
Commercial invoiceSellerCustoms valuation, payment evidence
Packing listSellerCase numbers, dimensions, gross/net weight — the basis of any damage claim
Bill of ladingCarrierTitle to the goods; telex release or original set, never "to be advised"
Certificate of originCCPIT / customsDuty preference under an FTA, if your country has one with China
Factory test reportManufacturerProves the set met nameplate before shipment
CE / conformity documentsManufacturer or notified bodyRequired for EU import; a self-declaration is not a test report
Insurance certificateInsurerOnly under CIF; under FOB/CFR you arrange your own
Fumigation / ISPM 15Supplier of packingRequired for solid wood packing; plywood cases are exempt

Ask for drafts before the vessel sails. Correcting a bill of lading after departure costs amendment fees and, worse, delays release at destination.

Packing: three methods and when each is right

Plywood case

The default for sets up to about 300 kVA. Fully enclosed, ISPM 15 exempt, stackable two high with a frame. Good against rain and dust, limited against impact. Add desiccant bags and a VCI film for humid destinations.

Steel frame with shrink wrap

Used for larger canopies and container modules that are too big to crate. Cheaper, but the set is visible and more exposed in transit — specify corner protection and edge boards or you will find paint damage on arrival.

Container loading, braced

For multiple units, or when the client buys the container. The set must be blocked against fore-aft movement with timber, not just chained: a 6 t set under braking generates a load that chains alone will not hold. We issue a loading plan with the centre of gravity marked.

Set sizePacked volume (approx.)20 GP40 HQ
30–50 kVA open2.6–3.2 m³9–11 units20–24 units
100 kVA silent4.0–4.6 m³6–7 units14–16 units
200 kVA silent6.5–7.5 m³4 units8–9 units
400 kVA silent11–13 m³2 units4–5 units
800 kVA container module20 ft module1 unit—

Volume, not weight, limits most genset shipments. That is why the canopy adds freight cost out of proportion to its price — a 100 kVA silent set takes about 60 % more container space than the open version.

HS classification and duty

Diesel generating sets over 75 kVA normally fall under HS 8502.13; sets up to 75 kVA under 8502.11. Generating set parts and separate alternators classify elsewhere. Duty rates vary widely by destination and by trade agreement — a wrong code is the most common cause of an unexpected customs bill, and it is worth confirming with your broker before the proforma invoice is signed, not after.

The three places buyers lose money

Payment terms that protect both sides

30/70 T/T is the market standard for gensets: 30 % to schedule production, 70 % against documents. For orders above USD 50,000, a letter of credit at sight is common and we accept it, provided the terms are workable — L/Cs that require a certificate from a third party not present at the test are a recipe for discrepancies. We will tell you at order stage which clauses will cause trouble rather than discovering it at negotiation.

Tell us the destination port and we will quote FOB, CFR and CIF

Send the load list and the port. You get three price lines, a loading plan and a document checklist — within two working hours, GMT+8.

Request a quotation See price guide

Questions buyers ask

Can you ship a single set by LCL?

Yes, for sets up to about 200 kVA. LCL is cheaper per unit but means more handling, so specify a plywood case and take photographs at handover. Above 200 kVA the volume usually makes a 20 ft FCL cheaper and much safer.

Who arranges insurance?

Under CIF we do, at 110 % of invoice value, all-risks. Under FOB or CFR you do — and you should, because carrier liability is limited by package, not by value. A genset that falls off a truck is not covered by the carrier's standard limit.

What warranty applies and where is it honoured?

Twelve months from commissioning or 1000 running hours, whichever comes first, on manufacturing defects. Parts ship from Liuzhou by air; labour is covered where we have a service partner and reimbursed at an agreed rate elsewhere. Wear items — filters, belts, injectors — are excluded, which is normal.

How do we handle a damage claim?

Note it on the delivery receipt before signing, photograph the case and the set, and notify us within 48 hours. The packing list case numbers and the photos decide the claim. Claims raised after the receipt is signed clean are very hard to win.

Related: how to verify a supplier before paying · price guide · maintenance and service contracts · silent canopy gensets · Vietnam · Tay Ninh import requirements · all diesel generator sets 8–4000 kVA