How a diesel generator ships from China: documents, packing and the cost nobody quotes
Most first-time import problems are not technical. They are paperwork, packing and port charges. This page walks through an order from deposit to arrival, names the documents you should receive, and flags the three places where buyers commonly lose money.
The order, step by step
- Load list and specification. You send required kW, voltage, frequency, application, altitude, ambient and destination port. We return a specification with a single-line diagram for review. This is where 80 % of later disputes are prevented — the voltage and rating definition must be written down, not assumed.
- Proforma invoice. Fixes the model, configuration, price, incoterm, payment terms, lead time and warranty. Check the alternator and engine serial prefix here, not after arrival.
- Deposit and production. Normally 30 % T/T in advance. Lead time is 15–25 days for stock ratings, 30–45 days for container modules or non-standard voltage.
- Factory test. Load test to nameplate with a printed report, plus a video for remote buyers. Insist on the serial number appearing on the report — a test sheet without it proves nothing.
- Balance payment and booking. 70 % before shipment, or against a copy of the bill of lading if the terms say so. We book the vessel and issue the loading plan.
- Documents and arrival. Originals or telex release, then destination clearance, then delivery to site and commissioning.
The document set
| Document | Issued by | What it does |
|---|---|---|
| Commercial invoice | Seller | Customs valuation, payment evidence |
| Packing list | Seller | Case numbers, dimensions, gross/net weight — the basis of any damage claim |
| Bill of lading | Carrier | Title to the goods; telex release or original set, never "to be advised" |
| Certificate of origin | CCPIT / customs | Duty preference under an FTA, if your country has one with China |
| Factory test report | Manufacturer | Proves the set met nameplate before shipment |
| CE / conformity documents | Manufacturer or notified body | Required for EU import; a self-declaration is not a test report |
| Insurance certificate | Insurer | Only under CIF; under FOB/CFR you arrange your own |
| Fumigation / ISPM 15 | Supplier of packing | Required for solid wood packing; plywood cases are exempt |
Ask for drafts before the vessel sails. Correcting a bill of lading after departure costs amendment fees and, worse, delays release at destination.
Packing: three methods and when each is right
Plywood case
The default for sets up to about 300 kVA. Fully enclosed, ISPM 15 exempt, stackable two high with a frame. Good against rain and dust, limited against impact. Add desiccant bags and a VCI film for humid destinations.
Steel frame with shrink wrap
Used for larger canopies and container modules that are too big to crate. Cheaper, but the set is visible and more exposed in transit — specify corner protection and edge boards or you will find paint damage on arrival.
Container loading, braced
For multiple units, or when the client buys the container. The set must be blocked against fore-aft movement with timber, not just chained: a 6 t set under braking generates a load that chains alone will not hold. We issue a loading plan with the centre of gravity marked.
| Set size | Packed volume (approx.) | 20 GP | 40 HQ |
|---|---|---|---|
| 30–50 kVA open | 2.6–3.2 m³ | 9–11 units | 20–24 units |
| 100 kVA silent | 4.0–4.6 m³ | 6–7 units | 14–16 units |
| 200 kVA silent | 6.5–7.5 m³ | 4 units | 8–9 units |
| 400 kVA silent | 11–13 m³ | 2 units | 4–5 units |
| 800 kVA container module | 20 ft module | 1 unit | — |
Volume, not weight, limits most genset shipments. That is why the canopy adds freight cost out of proportion to its price — a 100 kVA silent set takes about 60 % more container space than the open version.
HS classification and duty
Diesel generating sets over 75 kVA normally fall under HS 8502.13; sets up to 75 kVA under 8502.11. Generating set parts and separate alternators classify elsewhere. Duty rates vary widely by destination and by trade agreement — a wrong code is the most common cause of an unexpected customs bill, and it is worth confirming with your broker before the proforma invoice is signed, not after.
The three places buyers lose money
- Destination charges. A CIF quote covers freight to your port, not the terminal handling, THC, documentation, demurrage or clearance at your end. On a 20 ft shipment these can equal 10–15 % of the freight. Ask your broker for an estimate before you compare quotes.
- Demurrage at origin. If documents are late or the balance payment does not clear, the container sits at the port and the clock runs. Agree the payment trigger in writing.
- Fumigation and re-packing. Solid wood packing without ISPM 15 marking gets refused or fumigated at your cost. Specify plywood cases, or confirm the wood is treated and stamped.
Payment terms that protect both sides
30/70 T/T is the market standard for gensets: 30 % to schedule production, 70 % against documents. For orders above USD 50,000, a letter of credit at sight is common and we accept it, provided the terms are workable — L/Cs that require a certificate from a third party not present at the test are a recipe for discrepancies. We will tell you at order stage which clauses will cause trouble rather than discovering it at negotiation.
Tell us the destination port and we will quote FOB, CFR and CIF
Send the load list and the port. You get three price lines, a loading plan and a document checklist — within two working hours, GMT+8.
Request a quotation See price guideQuestions buyers ask
Can you ship a single set by LCL?
Yes, for sets up to about 200 kVA. LCL is cheaper per unit but means more handling, so specify a plywood case and take photographs at handover. Above 200 kVA the volume usually makes a 20 ft FCL cheaper and much safer.
Who arranges insurance?
Under CIF we do, at 110 % of invoice value, all-risks. Under FOB or CFR you do — and you should, because carrier liability is limited by package, not by value. A genset that falls off a truck is not covered by the carrier's standard limit.
What warranty applies and where is it honoured?
Twelve months from commissioning or 1000 running hours, whichever comes first, on manufacturing defects. Parts ship from Liuzhou by air; labour is covered where we have a service partner and reimbursed at an agreed rate elsewhere. Wear items — filters, belts, injectors — are excluded, which is normal.
How do we handle a damage claim?
Note it on the delivery receipt before signing, photograph the case and the set, and notify us within 48 hours. The packing list case numbers and the photos decide the claim. Claims raised after the receipt is signed clean are very hard to win.